Hand over the accepted BOM revision
Keep the accepted drawing and material requirement with the affected orders. Engineering chooses applicability and the disposition of old components. This sheet does not perform a CAD import or certify a design.
Worked example
Illustrative change: display D-10 becomes D-12 in revision B. Ten D-10 displays are already issued to an open job. Identify the job and authorised old-stock decision before issuing replacement material.
Use with your records
| Product and drawing | Item, accepted drawing/BOM revision and attachment reference ________________________________ |
|---|---|
| Change | Old component, new component, quantities and units ________________________________ |
| Applicability | Affected orders, effective basis and authorising person ________________________________ |
| Work already released | Open job, operation and quantities completed/in progress ________________________________ |
| Material already issued | Item/lot, issue record and quantity ________________________________ |
| Old-stock disposition | Authorised use, return, rework or other documented decision ________________________________ |
| Next records | Required revised job, purchase, issue or return reference ________________________________ |
| Handover | Engineering, planning and stores acknowledgement / open issue ________________________________ |
Print from your browser or retain a copy with the relevant work. Examples are illustrative. Keep original records and authorised decisions.