5 Steps to Review a Master Production Schedule in a Factory
Review the time-phased end-item plan against demand, capacity, material and protected changes before releasing work.

A master production schedule is a time-phased plan for selected finished goods. Before releasing jobs, check that its quantities and dates still fit demand, capacity and material constraints.
1. Confirm the demand and horizon
Check which orders or forecast assumptions the plan covers and which dates are inside the period you are reviewing. Record what changed since the last approved plan.
2. Check the calendar capacity
Illustration: an 8-hour shift with 1 hour of planned maintenance leaves 7 hours for production. A planned operation needing 8 hours does not fit in that shift as shown. Revisit the sequence, another eligible shift or the date rather than assuming the plan is feasible.
Optiwise supports machine calendars, shifts, worker skills and availability for planner review. See the capacity planning worksheet.
3. Check the material implications
Use the BOM and current usable stock, existing production and open purchase supply to identify shortages or late dates. Quality-held stock should not be counted as available until released.
See the MRP guide for the component requirement and exception path.
4. Protect decisions that need approval
Keep the planner's time fence or approval rule visible. If a near-term commitment changes, record who reviewed the change and which orders or components are affected.
5. Release and review the result
Release the agreed work, then compare actual progress with the plan. When material, capacity or demand changes, update the source record and review the affected period again. ASCM's master scheduling glossary describes review and adjustment as part of master scheduling.
FAQ
Does the MPS automatically make a feasible schedule?
No. A schedule depends on accurate inputs and reviewed capacity, material and business rules. The planner owns the decision to change or release it.
How often should we review it?
Use the review cadence and time fences appropriate to your order commitments and planning process. Recheck sooner when an important demand, supply or capacity input changes.
Related Posts

Food Rework Traceability From the Tub to the Receiving Batch
Trace an approved food rework tub into the receiving batch. Record what was issued, used, returned and held with a worked quantity example.
4 Nov 2026Read more →
How to Trace a Regrind Bag Before It Reaches the Hopper
Trace a recovered resin bag through weighing, job issue and actual hopper entry. Resolve a missing grade or source lot before approving reuse.
4 Nov 2026Read more →
Splitting a Supplier Lot Across Containers Without Double Counting
Follow a supplier lot through two container splits. Reconcile actual stock, retire the emptied tote and keep held pieces visible in Optiwise.
4 Nov 2026Read more →
Solder Paste Tracking: Keep Each Jar’s Storage and Opening History
Track solder-paste jars beyond the expiry date. Keep storage removal, opening, job issue and returned paste linked, with a worked timing example in Optiwise.
3 Nov 2026Read more →