Recheck a Dispatch Promise After an Inspection Delay
Recalculate dispatch readiness when final inspection slips. Check packing, paperwork and pickup cutoff before sales confirms a revised customer promise.

When an inspection finish time changes, check the remaining release, packing, document and transport steps before confirming dispatch. Keep the planner’s readiness estimate separate from the date the customer has accepted.

Work back from the pickup cutoff
Suppose a customer order for 100 units has a 16:00 pickup. The dispatch team needs two hours to pack the released goods and another 30 minutes to finish the documents and loading checks. In this illustrative sequence, packing starts after final inspection releases the goods, and the document and loading checks follow packing. The latest release time is 13:30.
Your actual steps may overlap or take different times. Record their dependencies and the people confirming them before using this calculation. Check whether the transport cutoff refers to loading completion, gate exit or a carrier booking deadline.
Recalculate when quality gives a later time
The final inspection is now expected to finish at 15:00. Even if all 100 units pass then, two hours of packing and 30 minutes of final checks give an earliest estimated loading completion of 17:30. That misses the 16:00 pickup by 90 minutes.
Quality’s expected finish time is still an estimate. Ask for the inspection result before counting the units as released. Dispatch checks whether the transport booking can move, and sales checks what the customer will accept. Keep the earlier promise in the order history when you record a revision.
| Step | Original plan | After inspection delay |
|---|---|---|
| Quality release | 13:30 | 15:00 expected |
| Packing complete | 15:30 | 17:00 earliest estimate |
| Documents and loading checks complete | 16:00 | 17:30 earliest estimate |
| Pickup cutoff | 16:00 | 16:00, unless transport confirms a change |
Decide whether a partial release helps
Suppose quality can release 70 of the 100 units earlier while 30 stay under review. A partial shipment becomes an option only after the customer and responsible commercial owner accept it, dispatch confirms the packing and documents for that quantity, and transport confirms space and timing. Recalculate the work for 70 units. Do not assume packing will take exactly 70% of the full-order time.
Keep the remaining 30 on the order with their inspection state and next update. A proposed later pickup is not a new confirmed customer promise. Wait for the customer and transport decisions before recording it as agreed.
Connect the new promise to the factory records
In Optiwise, your sales order connects the accepted customer requirement with production, dispatch, invoices and payment events. Your planner checks job progress and the relevant quality result. Dispatch follows the released goods and the linked transport request or trip. Sales records the customer’s accepted change with its supporting message or document.
Use configured fields or a linked readiness review for the last inspection update, packing estimate, cutoff, next owner and agreed follow-up time. If the inspector has not given a finish time, leave it open and ask for the next update. Our sales-order change guide covers the quantity balance after the customer changes an order. The dispatch-planning guide covers the wider readiness queue.
Microsoft’s delivery-date documentation distinguishes the calculations behind available-to-promise dates. For the example here, the calculation is a manual check of the remaining factory steps. Your team still confirms the actual release and transport commitment.
Questions before sales calls the customer
Does finished production mean the order can leave?
Check the required quality release, packing, documents and transport. Production completion is one input to the dispatch decision.
Should sales immediately promise the next day?
Confirm the remaining factory work and a usable transport booking first. Record the customer’s acceptance of the revised commitment.
Book an Optiwise factory walkthrough and bring one order whose dispatch promise changed. We can follow the records and the decision with your team.
Related Posts

Sales Invoice Management for a Part Payment and Dispute
Track invoice, allocated receipts and the disputed balance separately. Give each open amount a clear next step and owner.
5 Jun 2026Read more →
How Do I Manage Custom Furniture Orders?
Learn how furniture manufacturers can manage custom orders using specifications, drawings, approvals, BOMs, materials, cutting, CNC, assembly, finishing, costing, delivery, and installation tracking.
21 May 2026Read more →
Minimum Order Quantity | Optiwise
Learn minimum order quantity, why suppliers set MOQ, how manufacturers should evaluate it, risks, examples, and how Optiwise improves MOQ and stock planning.
2 May 2026Read more →
MSME networking events and trade fairs 2024: International opportunities for Indian businesses
Written by Reading progress Call us As we step into 2024, the landscape for Micro, Small, and Medium Enterprises (MSMEs) is evolving rapidly. With digital transformation becoming the norm, it’s crucial for Indian busines…
17 Apr 2026Read more →